JBC vs. FIDIC: Choosing the Right Contract

One of the most critical decisions in any construction project happens before ground is broken: selecting the Standard Form of Contract. Here is a comparative guide for Kenyan Developers:

Feature JBC "Green Book" FIDIC (Red Book)
Primary Use Private Building Works (Housing, Offices) Infrastructure & International Projects
Administrator The Architect The Engineer
Claims & Notices Flexible; implies "Reasonable time" Strict 28-Day Time Bar (Fatal if missed)
Dispute Resolution Arbitration (Often Slower) Dispute Adjudication Board (Immediate)
Inflation (Fluctuations) JBC Schedule of Basic Rates Central Bank / KNBS Indices